Project Status: IN CONSTRUCTION

Screenshot 2023-08-03 at 11.52.13 AM.png

Location: El Segundo Boulevard, between Illinois Street and Isis Avenue

Construction: October 2023 to April 2024

Investment: $6M in Construction Costs

OVERVIEW

The El Segundo Boulevard Improvement Project consists of furnishing all supervision, materials, labor, equipment, tools and incidentals for pavement rehabilitation, sidewalk and curb ramp construction and reconstruction, traffic signal modifications, signing and striping, landscaping and irrigation and drainage modifications on El Segundo Boulevard, Continental Boulevard, Nash Street, and Douglas Street (not including the intersection of PCH) as required in the specifications and contract documents for the following project: “El Segundo Boulevard Improvement Project”.

Project Features Include:

El Segundo Boulevard, between Illinois Street and Isis Avenue

  • Traffic Signal Upgrades

  • ADA Ramp and Sidewalk Improvements

  • Street Rehabilitation

  • Bike Lane Installation (Class II, Class III, and Cycle Track)

  • Median Landscape Improvements

Nash Street, between El Segundo Boulevard and Imperial Highway

  • ADA Ramp and Sidewalk Improvements

  • Street Rehabilitation

  • Bike Lane Installation (Class II, and Class III)

Douglas Street, between Rosecrans Avenue and Imperial Highway

  • Microsurfacing / Street Repair

  • Bike Lane Installation (Class II, and Class III)

Continental Boulevard, between El Segundo Boulevard and Grand Avenue

  • Bike Lane Installation (Class III)

PROJECT STATUS

Project construction will occur from October 2023 to April 2024. View the project schedule here. This information has been updated as of 3/20/2024.

  • The El Segundo Boulevard Improvement Project will start the pavement rehabilitation process on March 21, 2024. The repaving activity will take place on El Segundo Blvd. between Illinois Street and Isis Avenue, and  is expected to take approximately 1-month to complete, weather permitting.  The pavement repair is not a typical pavement overlay that occurs on most projects and will require repairs to the structural base of the roadway.  Due to this process, some lanes will need to be closed for longer periods of time.  At least one lane will remain open at all times in all directions.

  • The City is continually working on the traffic signal flow, as the traffic signals have been affected by the design upgrades on this project.  The traffic signals will be fully restored once the project is completed.  Commuters should expect delays and consider taking alternative routes.  Please exercise caution and patience while on the roadways.

PROJECT SCHEDULE

Project construction will occur from October 2023 to April 2024. View the project schedule here along with this projects latest look aheads which can be found in the Construction Updates section below. 

PROJECT HISTORY

  • January 2023 project awarded

  • October 2023 Construction Begins

  • February 2024 Estimated Construction Completion

  • May 2024 Landscape Maintenance and Establishment

  • Week of October 16 construction begun. See project schedule above, including weekly look aheads here.

  • The current work plan is as follows:

  • PHASE 1 - March 21, 2024 - April 1, 2024

  • Westbound Direction - lanes closest to the median will be closed to traffic.  At least 1 lane in the westbound direction will be open for vehicular traffic.

  • Eastbound Direction - lanes closest to the sidewalk will be closed to traffic.  At least 1 lane in the eastbound direction will be open for vehicular traffic.

  • PHASE 2 - April 1, 2024 - April 12, 2024

  • Westbound Direction - lanes closest to the sidewalk will be closed to traffic.  At least 1 lane in the westbound direction will be open for vehicular traffic.

  • Eastbound Direction - lanes closest to the median will be closed to traffic.  At least 1 lane in the eastbound direction will be open for vehicular traffic.

  • PHASE 3 - April 1, 2024 - April 30, 2024

  • All directions - intermittent closures - at least one lane open in all directions.  

  • Nash Street and Douglas Street will also be affected.

CONSTRUCTION UPDATES

PHOTOS & VIDEOS

RESOURCES

Subscribe for Weekly Construction Updates on the El Segundo Blvd Improvement Project

Thanks for subscribing!

SUBSCRIBE

Project construction will occur from June 2019 to summer 2022. Please see the Construction Updates and the Shifting Gears newsletter below for project progress.

The $113 million construction investment is funded by a combination of state, federal and local sources, including Measure A, the voter-approved half-cent sales tax for transportation improvements in Riverside County.

Contact Us

Address

350 Main Street  

El Segundo, CA 90245

Contact

Senior Construction Inspector

Thomas Dawson

949-274-0561

  • Facebook
  • Twitter
  • LinkedIn
  • Instagram

Construction Hours

Mon - Fri

7:00 am – 4:00 pm

bottom of page