Project Status: IN CONSTRUCTION
Location: El Segundo Boulevard from Whiting Street to Illinois Street
Construction: September 2023 to Winter 2024
Investment: $138.4 Million; $113 Million in Construction Costs
Jobs Created: 120
OVERVIEW
The El Segundo Boulevard Improvement Project consists of furnishing all supervision, materials, labor, equipment, tools and incidentals for pavement rehabilitation, sidewalk and curb ramp construction and reconstruction, traffic signal modifications, signing and striping, landscaping and irrigation and drainage modifications on El Segundo Boulevard, Continental Boulevard, Nash Street, and Douglas Street as required in the specifications and contract documents for the following project: “El Segundo Boulevard Improvement Project”.
PROJECT STATUS
Project construction will occur from June 2019 to summer 2022. Please see the Construction Updates and the Shifting Gears newsletter below for project progress.
The $113 million construction investment is funded by a combination of state, federal and local sources, including Measure A, the voter-approved half-cent sales tax for transportation improvements in Riverside County.
Shifting Gears Newsletter — Summer 2022
Shifting Gears Newsletter — Winter 2022
Shifting Gears Newsletter — Spring/Summer 2021
Shifting Gears Newsletter — Winter 2020
Shifting Gears Newsletter — Summer 2020
Shifting Gears Newsletter — Winter/Spring 2020
Shifting Gears Newsletter — October 2019
Shifting Gears Newsletter — September 2019
Shifting Gears Newsletter — August 2019
PROJECT SCHEDULE
Construction will take place from June 2019 to summer 2022. View the schedule and staging exhibits from open houses held in June 2019.
PROJECT HISTORY
June 2014: Caltrans issues the Final Initial Study with Mitigated Negative Declaration/Environmental Assessment with Finding of No Significant Impact.
October 2015: Caltrans issues the Recirculated Initial Study with Proposed Mitigated Negative Declaration/Environmental Assessment.
November 2015: Caltrans hosts public hearing for the Recirculated Initial Study with Proposed Mitigated Negative Declaration/Environmental Assessment.
May 2016: RCTC approves the Environmental Impact Report and is challenged in state court by a group of plaintiffs.
June 2018: RCTC resolves litigation for project – Click here for more information.
June 2018: RCTC begins advertising for construction management services.
October 2018: RCTC begins advertising for construction bids.
December 2018: RCTC awards contract for construction management services.
January 2019: RCTC awards construction contract.
August 2019 – March 2020: Six month westbound lane closure to complete the project one year earlier than originally planned.
Summer 2022 – Anticipated opening of new lanes.
May 12, 2023
May 5, 2023
Week of April 10, 2023
Week of February 13, 2023
Week of February 6, 2023
Week of July 11, 2022
Week of June 27, 2022
Week of June 20, 2022
Week of June 6, 2022
Week of May 30, 2022
Week of May 16, 2022
Week of May 9, 2022
Week of May 2, 2022
Week of April 25, 2022
CONSTRUCTION UPDATES
PHOTOS & VIDEOS
Describe your image
Describe your image
Describe your image
Describe your image
RESOURCES
Request Plans and Specifications
El Segundo Boulevard Improvement Project Vicinity Map
News
CONTACT US
Project construction will occur from June 2019 to summer 2022. Please see the Construction Updates and the Shifting Gears newsletter below for project progress.
The $113 million construction investment is funded by a combination of state, federal and local sources, including Measure A, the voter-approved half-cent sales tax for transportation improvements in Riverside County.