Project Status: IN CONSTRUCTION
OVERVIEW
The El Segundo Boulevard Improvement Project consists of furnishing all supervision, materials, labor, equipment, tools and incidentals for pavement rehabilitation, sidewalk and curb ramp construction and reconstruction, traffic signal modifications, signing and striping, landscaping and irrigation and drainage modifications on El Segundo Boulevard, Continental Boulevard, Nash Street, and Douglas Street (not including the intersection of PCH) as required in the specifications and contract documents for the following project: “El Segundo Boulevard Improvement Project”.
Project Features Include:
El Segundo Boulevard, between Illinois Street and Isis Avenue
-
Traffic Signal Upgrades
-
ADA Ramp and Sidewalk Improvements
-
Street Rehabilitation
-
Bike Lane Installation (Class II, Class III, and Cycle Track)
-
Median Landscape Improvements
Nash Street, between El Segundo Boulevard and Imperial Highway
-
ADA Ramp and Sidewalk Improvements
-
Street Rehabilitation
-
Bike Lane Installation (Class II, and Class III)
Douglas Street, between Rosecrans Avenue and Imperial Highway
-
Microsurfacing / Street Repair
-
Bike Lane Installation (Class II, and Class III)
Continental Boulevard, between El Segundo Boulevard and Grand Avenue
-
Bike Lane Installation (Class III)
PROJECT STATUS
Project construction will occur from October 2023 to April 2024. View the project schedule here. This information has been updated as of 4/30/2024.
-
PHASE 1 - March 21, 2024 - April 1, 2024
-
Work completed.
-
-
PHASE 2 - April 1, 2024 - April 12, 2024
-
Work completed.
-
-
PHASE 3A - April 22, 2024 - April 30, 2024
-
LOCATION: El Segundo Blvd, between Isis Ave and Illinois Ave.
-
The pavement overlay and restoration will begin. As of now, this operation is expected to be nightwork. At least one lane each direction will be open for vehicular traffic.
-
-
PHASE 3B - April 29, 2024 - May 2, 2024
-
LOCATION: And Nash St between Imperial Hwy and El Segundo Blvd.
-
The pavement overlay and restoration will begin. As of now, this operation is expected to be nightwork. At least one lane each direction will be open for vehicular traffic.
-
-
PHASE 4 - May 4, 2024 - May 5, 2024: WEEKEND WORK
-
LOCATION: Douglas St, between Imperial Hwy and Rosecrans Ave.
-
The pavement restoration will begin. At least one lane will be open for vehicular traffic in each direction.
-
-
PHASE 5 - May 1, 2024 - May 10, 2024:
-
Striping & signage restoration
-
Traffic signal restoration
-
-
The City is continually working on the traffic signal flow, as the traffic signals have been affected by the design upgrades on this project. The traffic signals will be fully restored once the project is completed. Commuters should expect delays and consider taking alternative routes. Please exercise caution and patience while on the roadways.
PROJECT SCHEDULE
Project construction will occur from October 2023 to April 2024. View the project schedule here along with this projects latest look aheads which can be found in the Construction Updates section below.
PROJECT HISTORY
-
January 2023 project awarded
-
October 2023 Construction Begins
-
February 2024 Estimated Construction Completion
-
May 2024 Landscape Maintenance and Establishment
-
Week of October 16 construction begun. See project schedule above, including weekly look aheads here.
CONSTRUCTION UPDATES
PHOTOS & VIDEOS
RESOURCES
SUBSCRIBE
Project construction will occur from June 2019 to summer 2022. Please see the Construction Updates and the Shifting Gears newsletter below for project progress.
The $113 million construction investment is funded by a combination of state, federal and local sources, including Measure A, the voter-approved half-cent sales tax for transportation improvements in Riverside County.
Contact Us
Address
350 Main Street
El Segundo, CA 90245
Contact
Senior Construction Inspector
Thomas Dawson
949-274-0561
Construction Hours
Mon - Fri
7:00 am – 4:00 pm